Kitchen
The plumbers removed some old drain pipes and vents. They began
installing pipes by patching up the radiant heat pipes that were broken
yesterday.

Dining Room
They poured the new footing and floor. Alex came back around 7 pm to
finish the floor.

Pool Area
In preparation for cutting the supports out from under it, they
stabilized the entire structure by scabbing on boards to tie the posts
together. Then they cut off the bottoms of the posts.